|
Market East Station
The regional rail station has four tracks
with diagonal colorful mosaics and skylights
giving a nice airy feel. Each track has two
boarding locations identified as Section A and
Section B but trains can arrive on any track in
any direction. It has connections to the
Convention Center, the
Market Frankford Line,
PATCO and the Ridge Spur
plus the underground concourse.
By Harry Kyriakodis
The two electrified rail networks
(Pennsylvania Railroad and Reading Railroad)
were not operationally integrated until
completion of the Commuter Rail Tunnel in
late 1984.
Officially known as the Center City Commuter
Connection (CCCC), the 1.7-mile long tunnel
essentially connected Suburban Station and
Reading Terminal. Both of these were inefficient
stub-end terminals that had formerly competed
for commuter traffic. The CCCC enabled the
through-routing of commuter trains and
eliminated capacity limitations and operational
difficulties imposed by stub end terminal
designs. This was a first for any U.S. city.
The project was first proposed in 1958 by R.
Damon Childs, a planner with the Philadelphia
Planning Commission. At first, city planner
Edmund Bacon was doubtful about the tunnel, but
he incorporated it into his 1960 Comprehensive
Plan for the city's future development once he
grasped the project's viability and usefulness.
Yet the widely-maligned tunnel was considered
for years to be a dream that would not come to
pass. Eventually, however, it was realized that
such a tunnel would greatly improve the Regional
Rail system's performance by allowing
Philadelphia's two original rail networks to
work together.
Ground was finally broken on June 22, 1978,
during Mayor Frank Rizzo's administration. The
$330 million project received 80 percent of its
funding from the Urban Mass Transit
Administration, now the Federal Transit
Administration.
The CCCC is a reinforced concrete box tunnel
of cut-and-cover construction. Its design and
construction were very challenging, as the
tunnel weaves both above and below pre-existing
subway lines. Also, several historic and
high-rise buildings along the route required a
great amount of underpinning. The 14-story City
Hall Annex (built in 1926; now the Marriott
Courtyard Hotel) needed special treatment, since
one track of the tunnel box passes directly
under the building's support columns along
Filbert Street.
The Masonic Temple, completed in 1873,
required an even stronger underpinning method
when cracks appeared in its ornate interior
plaster. To keep train noise and vibration from
disturbing downtown buildings and their
occupants, the subway's tracks use
continuously-welded rails on specially cushioned
concrete ties. Track level insulation and
acoustic panels between the four tracks further
deaden train noise. The concrete tunnel
structure itself is isolated from adjacent
structures by a two-inch layer of cork. In
addition, complex construction scheduling was
required to maintain vehicle, pedestrian and
rail traffic at street level and in the multiple
levels of subways and pedestrian concourses. And
there was a monumental relocation of utilities,
all of which had to be kept in service without
disruption.
The Commuter Rail Tunnel
actually lengthened the existing five-block
subway built by the Pennsylvania Railroad in the
late 1920s from Suburban
station towards
30th Street Station.
Thus, the entire rail tunnel is almost 2.5
miles long, right through the heart of Center
City Philadelphia.
Originally Suburban Station's
eight tracks ended at a concrete wall near 15th
Street. The CCCC extended four of the station's
tracks—two in each direction—eastward. The
tunnel project also included removing two of
Suburban Station's original tracks. In their
place, the two island platforms serving the
CCCC's through-tracks were widened to about
double their previous width. The rarely used
Track 0, a stub, shares a platform with the
southernmost Track 1, and there are three stub
tracks north of the four through-tracks. Several
trains can be seen on the stubs during mid-days.
Interestingly, although the station's four
through tracks are on the south side, Suburban
Station was originally designed so that its two
northernmost tracks could be extended east
towards a proposed tunnel under the Delaware
River to connect to Pennsylvania Railroad lines
out of Camden, New Jersey. This was never done.
Leaving Suburban Station, the tracks head
east through a small interlocking area and pass
over the Broad Street Subway.
Even though this north-south line was
designed to allow a future subway above it north
of City Hall, clearances were
barely adequate for the Commuter Rail Tunnel. A
20-foot wide section of subway roof was
demolished and a new one built while maintaining
Broad Street Subway service on at least two
tracks. Furthermore, a 400-foot length of SEPTA
Subway-Surface trolley line
parallel to the new tunnel was moved 16 feet
south. A new westbound 15th Street
trolley stop was also built, all while keeping
service running.
Next is Market East Station,
a $75 million transportation Center
completed in 1984. The Gallery's basement level
adjoins Market East Station's mezzanine. In
fact, this level of the Gallery extends the
city's underground pedestrian concourse network
all the way to 8th Street.
It is thus possible to walk entirely
underground in downtown Philadelphia from 19th
Street to 8th Street! The nearby
intersection of 8th and Market
Streets is a key transportation hub, with access
to stations for the Market
Street Subway, the Broad
Street Spur/Ridge Avenue Subway, and the
PATCO Hi-Speed line.
The Reading Company built One
Reading Center at 11th and Market Streets
contemporaneously with the Commuter Rail Tunnel.
This was the Reading Company's first substantial
effort in real estate development after quitting
the railroad business and emerging from
bankruptcy on January 1, 1981. Now known as the
Aramark Tower, the handsome edifice was
completed in 1984 and was the first major office
high-rise constructed on east Market Street in
fifty years. The building has 31 office floors
above two retail levels and incorporates special
curved corners and stepped terraces on the
exterior. Each of its dark reflective glass
façades was designed to respond to neighboring
buildings in a unique fashion. The tower's
11-story glass-enclosed lobby atrium contains an
art deco marble lobby, a reflecting pool and a
sculpture garden.
Reading Terminal's headhouse is
adjacent to the Aramark Tower. When Market East
Station opened, it effectively replaced the old
terminal's function. The CCCC passes under the
near-center of the Reading Terminal trainshed,
far below its elevation and perpendicular to it.
Special challenges arose here during the
tunnel's construction, since full commuter train
service had to be maintained inside the shed
while extensive underpinning was done below. The
historic trainshed is now part of the
Pennsylvania Convention Center, which was
constructed nearby (between Arch and Race
Streets from 11th to 13th Streets) in the early
1990s. SEPTA headquarters are across the street
from Reading Terminal, at 1234 Market Street,
next to the PSFS Building (now a Loews Hotel).
And the Philadelphia Greyhound bus terminal is
at 10th and Filbert Streets, very close to
Market East Station.
Commuter Rail Tunnel construction very much
disrupted Chinatown, under which the subway
curves north. The city and project engineers
worked closely with local residents and business
owners to solve business disruption, noise,
dust, parking and traffic flow problems. In
addition, the 9th and Vine Street station of the
Broad Street Spur/Ridge Avenue Subway lay
directly in the path of the tunnel and had to be
demolished. A replacement station was built near
8th and Race Streets as that line's Chinatown
stop. The lowest point of the CCCC is under this
station, about twenty feet below sea level. The
tunnel then passes under the Vine Street
Expressway near this spot. On the
northern side of the expressway, the
Philadelphia Chinatown Development Corporation
constructed a fine village of mixed-income
residences on the undesirable land alongside the
expressway from 8th to 9th Streets, with parking
and green space over the CCCC. This was a
creative way to comply with regulations
prohibiting heavy construction on land above a
subway.
Proceeding north, the tunnel rises on a steep
2.8 percent grade as it ends at the Green Street
portal. A few blocks later, the tracks connect
on a direct high-speed alignment to the old
elevated Reading main line—the 9th Street
Branch—that used to take trains into Reading
Terminal .
The southern part of this viaduct from Vine
Street to the Pennsylvania Convention Center was
torn down in the early 1990s since it was no
longer needed after the CCCC's completion.
|